- Carpentry - Kitchen entry ceiling exterior. Would like to cover up the stucco with a nice wood surface and new hanging light fixture. Would also like to look at the same situation with the front entry.
- Asbestos - We will start the abatement process for the asbestos that is currently in the guest bath. There is a 10 day waiting period before the removal can begin.
- Plumbing - We will set up a meeting with the plumber to go over the bath renovation scenarios this week.
- Radiators - We have designated 9 radiators to be removed and sent out for refinishing.
- 2 in kitchen
- 1 in laundry
- 1 under sink in pantry
- 2 in guest bed room
- 1 in guest bath
- 1 in hall outside guest bedroom
- 1 in hall bath
- Kitchen - Georgia today offered the following ideas:
- Leave existing windows and turn window at sink into a door.
- Have a sink against the door that rotates out 90 degrees
- Find a location for a couch or "papa" chair.
- Start flooring asap but after 9/21 if possible.
- We may or may not do the arch at the same time as the flooring.
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Monday, August 26, 2013
Meeting Notes 8/26/13